Safeguarding · Cranes and tall equipment

Cranes and tall equipment.

Cranes can affect aircraft operations well beyond the airfield boundary. Contact the airport with your proposal early, notify the CAA where required and apply through Air Portal before the lifting programme is finalised.

Coordinate the works early

Airport assessment is separate from CAA notification and other project approvals.

Step one

Put the right information in front of the airport early.

Contact Rochester Airport with your proposal before finalising the lifting programme. An early conversation confirms whether an application is needed, what the assessment will look at and how long to allow.

Applies to cranes, lifting activities and temporary obstacles such as piling rigs, scaffolding and mobile elevated work platforms near the airfield.

CAA crane notification

When the CAA needs to know.

The CAA uses ACOMS for crane notifications. Its guidance identifies the cranes that must be notified and the notice to allow.

Within 6 km of an airfield

10 m

Cranes exceeding 10 m above ground, or above surrounding structures or trees if higher

Anywhere

100 m

Cranes at or above 100 m above ground, regardless of location

Planned long-term projects

8 weeks

CAA recommended notice

Ad-hoc projects

5 working days

Minimum notice. Urgent projects have additional arrangements

Rochester’s own assessment time is separate from the CAA’s notice periods. Full guidance: CAA crane notification and the CAA portal (ACOMS).

How it works

Locate. Measure. Apply. Confirm.

Accurate heights and locations up front avoid delay.

01 · Locate

Define the work site

Provide the site address, precise crane coordinates and a site plan that identifies the operating area.

02 · Measure

Confirm maximum height

State ground elevation above mean sea level, maximum tip height above ground and the overall top elevation.

03 · Apply

Submit through Air Portal

Upload the dates, equipment details, contacts and supporting material required for assessment.

04 · Confirm

Receive the decision

Do not begin the operation unless the required approval has been issued and all stated conditions are met.

What to prepare

Accurate information avoids delay.


Site and contacts

Project, crane operator and on-site emergency contact details. Site address, precise crane coordinates and a site plan.


Equipment and height

Crane model, jib length, working radius and any relocation or out-of-service configuration. Ground elevation, maximum tip height above ground and overall top elevation.


Programme and lighting

Erection, operation and dismantling dates with daily time windows. Proposed lighting, lifting arrangements and the CAA / ACOMS reference where available.

After you apply

Permission must be confirmed.

Do not begin the proposed activity until the required permissions are in place and any conditions are understood. The equipment must not operate until the assessment is complete and all conditions have been accepted.

Tell the airport about changes to the location, height, dates or operating method.

Questions before you apply?

If you are unsure whether the work needs airport assessment, call 01634 869969 and the team will confirm the route and what to send.